Construction Timeline

From Permit to Punch List: A Complete Ground-Up Build Timeline for 2025

18 min read
Updated for 2025

Building from the ground up is an exciting journey, but a realistic timeline is crucial for success. This guide breaks down every phase for custom homes and commercial projects in Southern California, Arizona, and Utah.

Plan Your Project with Confidence

Get a detailed timeline and accurate cost estimate for your specific ground-up construction project. Our experts will help you navigate every phase.

Timeline Overview: Residential vs. Commercial

Typical Ground-Up Build Timelines for 2025

Custom Home (2,500 sq ft)

8-14 months total

Commercial Space (5,000 sq ft)

10-18 months total

These timelines are estimates. For a detailed cost breakdown, see our guide on how much it costs to build a custom home in 2025.

Phase-by-Phase Construction Breakdown

1
Pre-Construction Phase (2-6 months)

Design, engineering, and permitting. The most critical phase for budget and timeline success.

2
Site Preparation (2-4 weeks)

Surveying, excavation, grading, and utility trenching.

3
Foundation Work (2-4 weeks)

Pouring footings and foundation walls to create a solid base.

4
Rough Construction (8-16 weeks)

Framing, roofing, windows, and MEP (Mechanical, Electrical, Plumbing) rough-in.

5
Insulation & Drywall (3-5 weeks)

Closing up the walls and preparing for interior finishes.

6
Interior Finishes (6-10 weeks)

Flooring, paint, cabinets, countertops, and fixtures.

7
Final Systems & Exterior (2-4 weeks)

MEP finals, exterior siding, and hardscaping.

8
Final Inspections & Completion (1-2 weeks)

Punch list, final walkthrough, and receiving the Certificate of Occupancy.

How Location Impacts Your Timeline

Permitting and labor availability vary significantly by location. Here’s a quick overview:

Los Angeles & Orange County

Expect longer permit times (add 2-4 weeks) due to complex regulations, especially in coastal zones. High demand for skilled labor means booking contractors well in advance is crucial. Learn more about our services as a general contractor in Los Angeles.

San Diego County

Generally balanced timelines with year-round construction weather. Coastal Commission can add time to projects near the water. See our expertise as a general contractor in San Diego.

Arizona & Utah

Faster permitting but be mindful of seasonal weather. Extreme summer heat in Phoenix or winter snow in Flagstaff can impact schedules.

How to Keep Your Project On Schedule

  • Finalize Designs Early: Avoid change orders, which are a primary cause of delays and cost overruns.
  • Hire an Experienced Local Contractor: They understand local permit processes and have established relationships with inspectors.
  • Order Long-Lead Items Early: Custom windows, doors, and specialty fixtures should be ordered during the permit phase.
  • Budget for Contingencies: A 15-20% buffer in both your timeline and budget is essential.

For more tips, read our guide on the top 5 questions to ask any contractor.